Contract for “Supplementary works for Ordu Ring Road Section btw. Km: 21+000 – 42+414,784” project was signed

Contract for “Supplementary works for Ordu Ring Road Section btw. Km: 21+000 – 42+414,784” project was signed with General Directorate of Highways.New project, designed as 21,4 km highway having 2×2 lanes, consists of supplementary works for our already completed Ordu Ring Road project and scope comprises earthworks, engineering structures, tunnels, plant-mix subbase, plant-mix base and bituminous hot mix productions. The Contract Price is 584 Million TL and the duration of the project is 1100 days from the site handover.

We wish that the project will serve our country in a best possible way.