Emirates Engineering Center
Aircraft Hangar, Dubai/UAE
One hangar is
approximately composed
of;
2.000 tons of steel,
100.000 nuts,
20 km long welding,
300.000 holes
7.000 elements.
Using of HISTAR steel, all joints being slip
critical joints, fabrication of the construction
in Ankara’s cold weather by considering the
erection difficulties and 108 meters Mega
Truss deflections to be caused by the hot
Facade Truss’ big dimensions like 500 tons and 110 meters span, erection of this truss in one step,
weather in Dubai.The works have been
working of the 50 tons Monorail Cranes in 100 meters span length, critical paint procedures due to
completed within a period of 14 months.
Dubai’s humidity and climate, and torsioning of all 10,9 nuts according to DIN 18800 are the
significant properties of this Hangar, which make it very rare in the world.