Page 18 - Nurol YES Sustainability Report
P. 18
PROJECTS: ON-GOING AND
IN THE SCOPE OF REPORT
4 active on-going projects - Gebze - Orhangazi - İzmir Motorway, Balıkesir - Kırkağaç - Akhisar
Section, Konya Eyiste Viaduct Project, Algeria Boukhroufa Dam Project- and HQ are included in the
scope of Nurol Construction's sustainability report. Main reason for the inclusion of referred
projects is Nurol Construction is the main proprietor of these project. In other words, there is no
available partnerships for these projects. Thus, Nurol Construction is the sole proprietor for the
management of these projects and the main responsible from the performance and actions.
A liates and subsidiaries of Nurol Construction is not included in the report.
GEBZE-ORHANGAZI-IZMIR MOTORWAY
BALIKESIR-KIRKAGAÇ-AKHISAR SECTION PROJECT (BALIKESİR MOTORWAY PROJECT)
As per the implementation Section: 25,1 million m cut
3
3
contract signed on September excavation, 76 million m
2010 and e ective as of March borrow pit excavation, 25,8
3
2013 with General Directorate million m filling works,
3
for Highways and Highway 900.000 m concrete works, ALGERIA BOUKHROUFA DAM PROJECT ALGERIA SOUK TLETA DAM PROJECT
Investment and Enterprises Inc; 3.319 prestressed beams and
Nurol Construction is the 19.642 meters bored piles, 4.4 Boukhroufa Dam is under construction by Nurol Construction at Souk Tleta Dam is under construction by Nurol Construction at
undertaker of the project and million tons wetmix and 2.2 the El Tarf province of Algeria. It is located on the Boukhroufa the Tizi Ouzou province of Algeria. It is located on the
3
continues the Balıkesir - million tons hotmix, thus total Stream, 9 km south of the Bouteldja city, to provide 125 hm of Bougdoura Stream, 8 km south of the Draa Ben Khedda city, to
Kırkağaç - Akhisar Section of 6.6 million tons of irrigation water for agricultural lands in the region. The dam is a provide 90 hm of irrigation and drinking water for Tizi Ouzou
3
construction which is the superstructure production exist. clay core earth fill dam and it will be 87 m high from the and Boumerdes regions. The dam is a clay core earth fill dam
second phase of İzmir- Gebze On top of 5 bilateral motorway foundation. Once completed, its reservoir will have a and it will be 95 m high from the foundation. Once completed
3
3
Motorway project. 93 km facilities, in this section; there 125.000.000 m storage capacity. Project’s scope is 2.200.000 m its reservoir will have a 90.000.000 m storage capacity.
3
3
motorway and total 6 viaducts, are 5 intersections and 20 toll cut excavation, 4.800.000 m fill, 82.000 m concrete and 2.800 Project’s scope is 1.600.000 m cut excavation, 1.800.000 m 3
3
3
37 overpass bridges, 75 booths area connecting tons of reinforcement. In 2018, for the project: fill, 116.000 m concrete and 3.600 tons of reinforcement. In
3
underpass bridges, 224 box Balıkesir, Savaştepe, Soma, 2018, for the project:
culverts, 6 retaining walls and Kırkağaç and Akhisar sections.
10 diversion canals are under In 2018, for the project:
3
the scope of the project. 185.000 m cut excavation
3
1.100.000 m filling works 1.360.000 m cut excavation
3
4.600 m reinforced concrete production completed. 273.850 m filling works
3
3
3
4.770.000 m excavation 40.150 m grading works 1.960.000 tons of wet mix production for superstructure 3
4.839.000 m filling works 76.217 m reinforced concrete 852.000 tons of hot mix production for superstructure completion. 70.250 m reinforced concrete production completed.
3
3
Expected project completion: March 2021.
Expected project completion: August 2019. Expected project completion: April 2021.
KONYA EYİSTE VIADUCT PROJECT
The tender related to the Eyiste of 25 meters will be constructed;
Viaduct has been conducted by and it will be one of the world's
General Directorate of biggest balanced cantilever
Motorways, the contract has been viaduct. The superstructure will
awarded to Nurol Construction by be constructed on 2 abutments
end of 2016. Within the scope of and 8 piers with varying heights
the project, a bridge with a length between 31 meters and 155
of 1.372 meters and a total width meters. In 2018, for the project:
22.150 m cut excavation
3
560 m bored pile works
45.810 m reinforced concrete production
3
9.461 tons of reinforcement production completed.
Expected project completion: December 2022.
18 NUROL YES SUSTAINABILITY REPORT 2018 ON GOING PROJECTS 19