Page 18 - Nurol YES Sustainability Report
P. 18

PROJECTS: ON-GOING AND

                                 IN THE SCOPE OF REPORT









                            4 active on-going projects - Gebze - Orhangazi - İzmir Motorway, Balıkesir - Kırkağaç - Akhisar
                          Section, Konya Eyiste Viaduct Project, Algeria Boukhroufa Dam Project- and HQ are included in the
                             scope of Nurol Construction's sustainability report. Main reason for the inclusion of referred
                           projects is Nurol Construction is the main proprietor of these project. In other words, there is no
                            available partnerships for these projects. Thus, Nurol Construction is the sole proprietor for the
                             management of these projects and the main responsible from the performance and actions.
                                  A liates and subsidiaries of Nurol Construction is not included in the report.




          GEBZE-ORHANGAZI-IZMIR MOTORWAY
          BALIKESIR-KIRKAGAÇ-AKHISAR SECTION PROJECT (BALIKESİR MOTORWAY PROJECT)

          As per the implementation   Section:  25,1 million m  cut
                                                      3
                                                       3
          contract signed on September   excavation, 76 million m
          2010 and e ective as of March   borrow pit excavation, 25,8
                                            3
          2013 with General Directorate   million m  filling works,
                                              3
          for Highways and Highway   900.000 m  concrete works,                                                                  ALGERIA BOUKHROUFA DAM PROJECT                            ALGERIA SOUK TLETA DAM PROJECT
          Investment and Enterprises Inc;   3.319 prestressed beams and
          Nurol Construction is the   19.642 meters bored piles, 4.4                                                             Boukhroufa Dam is under construction by Nurol Construction at   Souk Tleta Dam is under construction by Nurol Construction at
          undertaker of the project and   million tons wetmix and 2.2                                                            the El Tarf province of Algeria. It is located on the Boukhroufa   the Tizi Ouzou province of Algeria. It is located on the
                                                                                                                                                                            3
          continues the Balıkesir -   million tons hotmix, thus total                                                            Stream, 9 km south of the Bouteldja city, to provide 125 hm  of   Bougdoura Stream, 8 km south of the Draa Ben Khedda city,  to
          Kırkağaç - Akhisar Section   of 6.6 million tons of                                                                    irrigation water for agricultural lands in the region. The dam is a   provide 90 hm  of irrigation and drinking water for Tizi Ouzou
                                                                                                                                                                                                      3
          construction which is the   superstructure production exist.                                                           clay core earth fill dam and it will be 87 m high from the   and Boumerdes regions. The dam is a clay core earth fill dam
          second phase of İzmir- Gebze   On top of 5 bilateral motorway                                                          foundation. Once completed, its reservoir will have a     and it will be 95 m high from the foundation. Once completed
                                                                                                                                            3
                                                                                                                                                                                3
          Motorway project. 93 km    facilities, in this section; there                                                          125.000.000 m  storage capacity. Project’s scope is 2.200.000 m    its reservoir will have a 90.000.000 m  storage capacity.
                                                                                                                                                                                                                       3
                                                                                                                                                                 3
          motorway and total 6 viaducts,   are 5 intersections and 20 toll                                                       cut excavation, 4.800.000 m  fill, 82.000 m  concrete and 2.800   Project’s scope is 1.600.000 m  cut excavation, 1.800.000 m   3
                                                                                                                                                      3
                                                                                                                                                                                                                 3
          37 overpass bridges, 75    booths area connecting                                                                      tons of reinforcement. In 2018, for the project:          fill, 116.000 m  concrete and 3.600 tons of reinforcement. In
                                                                                                                                                                                                     3
          underpass bridges, 224 box   Balıkesir, Savaştepe, Soma,                                                                                                                         2018, for the project:
          culverts, 6 retaining walls and   Kırkağaç and Akhisar sections.
          10 diversion canals are under   In 2018, for the project:
                                                                                                                                           3
          the scope of the project.                                                                                                 185.000 m  cut excavation
                                                                                                                                            3
                                                                                                                                    1.100.000 m  filling works                                 1.360.000 m  cut excavation
                                                                                                                                                                                                       3
                                                                                                                                    4.600 m  reinforced concrete production completed.        273.850 m filling works
                                                                                                                                          3
                                                                                                                                                                                                      3
                      3
             4.770.000 m  excavation  40.150 m grading works   1.960.000 tons of wet mix production for superstructure                                                                               3
             4.839.000 m  filling works  76.217 m  reinforced concrete  852.000 tons of hot mix production for superstructure completion.                                                      70.250 m  reinforced concrete production completed.
                      3
                                           3
                                                                                                                                 Expected project completion: March 2021.
          Expected project completion: August 2019.                                                                                                                                        Expected project completion: April 2021.
          KONYA EYİSTE VIADUCT PROJECT
          The tender related to the Eyiste   of 25 meters will be constructed;
          Viaduct has been conducted by   and it will be one of the world's
          General Directorate of       biggest balanced cantilever
          Motorways, the contract has been   viaduct. The superstructure will
          awarded to Nurol Construction by   be constructed on 2 abutments
          end of 2016. Within the scope of   and 8 piers with varying heights
          the project, a bridge with a length   between 31 meters and 155
          of 1.372 meters and a total width   meters. In 2018, for the project:
            22.150 m  cut excavation
                   3
            560 m bored pile works
            45.810 m  reinforced concrete production
                   3
            9.461 tons of reinforcement production completed.
          Expected project completion: December 2022.

           18   NUROL YES SUSTAINABILITY REPORT 2018  ON GOING PROJECTS                                                                                                                                                                19