PROJECTS: ON-GOING AND

                            OUT OF THE SCOPE OF REPORT







          GEBZE – ORHANGAZİ – İZMİR MOTORWAY PROJECT                                                                             ORDU RING MOTORWAY PROJECT
                                                                                                                                 The Ordu Ring Motorway is being constructed by NUROL-YÜKSEL-ÖZKA-YDA Joint Venture. The project consists of 21,4 km of 2x2 lanes split
          As per the implementation   centers, 3 tunnel operation and                                                            motorway with miscellaneous motorway structures of 5.3 km*2 length (3.3 km*2+2km*2) double tube, 3 viaducts total of 1.98 km length, 5
          contract signed on 27      maintenance centers and 18                                                                  bridges, 2 underpass and 3 crossover road along the route. The project completed in 2018.
          September 2010 between     bilateral motorway service
          General Directorate of     facilities (A type: 2, B Type: 4, C
          Motorways and Motorway     type: 5 and D Type: 7). Dilovası                                                            ORDU MOTORWAY CONNECTION PROJECT
          Investment and Operating Co.,   Intersection (km:0+000) and                                                            The project owner is Nurol-Yüksel-Özka-YDA Joint Venture and signed an additional agreement aiming to complete the remaining construction
          that became e ective on 15   İznik South Intersection                                                                  activities. According to the agreement, project is expected to be completed by 2022.
          March 2013 a total of 427 km   (km:58+152) are completed and
          motorway -384 km motorway &   opened to tra c, for the rest of
          43 km connection way- is being   the project construction                                                              SİLİFKE-MUT ROAD PROJECT
          constructed between Gebze and   continues. As per the                                                                  Under Nurol Construction's responsibility; Silifke-Mut Road will be completed for 16.7 km highway, having 2X2 road section together with tunnel
          izmir. The scope of the project   implementation contract,                                                             and engineering structures. 6.850 meters length of double tube and  410 meters II. Kılıçarslan Bridge (cable-stayed and balanced cantilever
          includes İzmit Bay Bridge, 29   construction period is 7 years                                                         beam method) are also under the scope of the project.
          viaducts, 3 tunnels, 199   after the contract became valid
          motorway bridges, 20 toll   and accordingly o cial project
          booths area, 25 Intersection, 6   completion date is March 2020.                                                       ILISU DAM AND HEPP PROJECT AND HASANKEYF
          operation and maintenance                                                                                              GROUP BRIDGES PROJECT

                                                                                                                                 Nurol- Cengiz Joint Venture   Nurol-Cengiz Joint Venture also
          PTO TİZİ OUZOU BOUİRA INTERSECTION MOTORWAY                                                                            established for the construction   established Nurol Cengiz
          PTO PROJECT                                                                                                            of Ilısu Dam and HEPP, located   Hasankeyf Partnership for the
                                                                                                                                 on Tigris River in Mardin, dam   completion of Hasankeyf Group
          The Tizi Ouzou-Bouira intersection with 48 km length is being
          constructed by Özgün-Nurol Joint Venture in Algeria.                                                                   will be constructed by concrete   Bridges Project considering the
          In 2018, for the project:                                                                                              face rockfill and the dam body   agreement dated 2013. Project
                                                                                                                                 volume will be 23,76 million m ,   includes construction of
                                                                                                                                                       3
                                                                                                                                 by 1.200 MWh capacity with   Hasankeyf-1, Hasankeyf-2,
             1.400.000 m  cut excavation
                      3
             470.000 m  fill                                                                                                      4.120 GWh yearly production.   Reşat Baysal and Başur
                     3
             75.000 m  reinforced concrete production                                                                            Dam foundation is 131 meters   Motorway Bridges in Batman
                    3
             346.000 m  tunnel excavation                                                                                        high and maximum water level   and Siirt cities. Project
                     3
                   3
             3.800 m  tunnel pavement concrete production                                                                        of 528.87 meters. Project   completion date is September
             185.000 tons of superstructure wet mix production                                                                   completion date is June 2019.   2019.
             231.000 tons of superstructure hot mix production completed.
          Expected project completion: 2023.                                                                                     UNITED ARAB EMIRATES PROJECTS
          YUSUFELİ DAM RESERVOIR VIADUCTS PROJECT                                                                                NUROL UAE, started business as a local firm in Abu Dhabi- the capital city of UAE- in April 2003. In 2004, Dubai branch opened. Founding
                                                                                                                                 purpose is to materialize high scope projects via benefiting from the current potential in construction industry.
          4 Viaducts, to be implemented by balanced
                                                                                           3
                                                             3
          cantilever beam method in Yusufeli District of Artvin   277.539 m  cut excavation  457.777 m  foundation excavation    Ongoing projects of Nurol UAE in Dubai and Abu Dhabi by end of 2018 are as below:
                                                                                         3
          City has assigned to Nurol-Gülsan Joint Venture by   33.873 m bolt production  452 m  plain concrete production,
          General Directorate of Motorways. The project began   13.191 m barbican production  718 tons of reinforcement working
                                                                                          3
          in 2017 and expected to be completed by 2021.   253 tons of matting steel production  3.562 m  reinforced concrete production   The Cove Dubai Gulf Building Project         Cordonnier Estate Building Project
          In 2018, for the project:                   22.408 tons of shotcrete production  completed.                            Located in Dubai, total construction area is 76.000 sqm and there will   Located in Abu Dhabi, with total construction area of 67.000 sqm,
                                                                                                                                 be 3 residence buildings.                             construction of tower including commercial, o ce and residence
                                                                                                                                 GA09 Golf Apartment Building Project                  sections will be completed.
          YEŞİLYAKA PROJECT                                                                                                                                                            GA14 Golf Link Villas Project
                                                                                                                                 Located in Dubai, 288 (108X1, 132X2, 32X3, 2X4 Bedroom and 14
          Yeşilyaka project contains the construction villas, social facility, sales o ce and trading area, around Büyükçekmece Sırtköy district on   detached house) apartment (Z+11) construction will be completed.  Located in GA14 region in South Emaar, construction of 204 villas will
                   2
          1.000.000 m  land. For the Yeşilyaka Project Mesa- Nurol Joint Venture established.                                    P32 Parcel Dubai Gulf Building                        be completed by 2020.
                                                                                                                                                                                       Dubai Vista Beach Residential Towers Project
          ÜMRANİYE ATAŞEHİR GÖZTEPE METRO PROJECT                                                                                Located in Dubai, construction of twin towers including 471 residen-
                                                                                                                                 ces will be completed                                 Located in Dubai Harbor, residential towers (2) will be completed by
          The project consists of the construction of a 13 km long double tube TBM tunnel along with 2 train storage tunnels and a connection tunnel.                                  2021.
          There are 11 stations within the scope of the project, 5 of which being shaft+tunnel type. Construction scope is architectural and
          electromechanical installment. For this project, Gülermak-Nurol-Makyol Joint Venture established.