Page 26 - Nurol Construction Company Presentation
P. 26
İstanbul Metro Project -
Phase 1 Section 1
(Şişli – 4.Levent),
İstanbul/TURKEY:
The İstanbul Metro Project
Phase 1 was executed by
Metro-1 Joint Venture in
which NUROL has 30%
share. There are 3 stations
on the route. It is one of the
earliest metro lines in
İstanbul.
The excavation depth varies between 20-30 m and the total tunnel length (formed of
double tunnels) is 8.250 m (concreted inner diameter of tunnels: 5,40 m)