Kürtün Dam
and HEPP,
Kürtün Dam, the first Concrete
Faced Rockfill Dam of Turkey was Gümüşhane/
constructed in a remote area
where winter conditions are harsh. TURKEY
The dam has an underground
power station. Installed capacity is
85 MW. Height from foundation is
133 m and Crest length is 380 m.
First RCC dam application in
Turkey was also included in the
project scope(Upstream
Cofferdam).