PROJECTS: ONGOING AND IN UMRANIYE ATASEHIR GOZTEPE METRO LINE PROJECT
Within the scope of our Umraniye-Atasehir-Goztepe Metro Project, which was
THE SCOPE OF REPORT undertaken in 2017 by the contract signed with Istanbul Metropolitan Municipality,
13 km long double tube, single line TBM tunnel, 2 train depots (NATM) and
connection tunnel (NATM) will be constructed. There are a total of 11 stations in the
ALGERIA SOUK TLETA DAM PROJECT Project, 5 of which are of the main shaft + tunnel type, 4 of which are cut-and-cover
Souk Tleta Dam is under the construction by Nurol Construction at the Tizi Ouzou type and 2 are of the tunnel type. With the completion of the metro route under the
province of Algeria. It is located on the Bougdoura Stream, 8 km south of the contract, 3 districts on the Anatolian side of Istanbul will be connected.
Draa Ben Khedda city, to provide irrigation and drinking water for Tizi Ouzou and
Boumerdes regions. The dam is a clay core rock fill dam, and it will be 88,70 m high
3
from the foundation, once completed its reservoir will have 98,000,000 m capacity. Umraniye Atasehir In 2022, for the Project:
3
Goztepe Metro Line 433,705.03 m cut excavation works
3
In 2022, for the Project: In the Project as of the end of 2022, total: Project 69,372.23 m reinforced concrete works
348 m cut excavation works 1,458,671 m cut excavation works 11,033.52 tons reinforcement works
3
3
3
27,012 m filling works 348,300 m filling works 4,974.80 m TBM tunnel works
3
17,796 m injection works 47,685 m injection works 1,923 pieces segment works was completed.
2,694 m reinforced concrete works was completed. 132,654 m reinforced concrete works completed.
3
3
In the Project as of the end of 2022, total:
Expected project completion: July 2026. 2,366,321 m cut excavation works
3
3
276,507 m reinforced concrete works
44,241 tons reinforcement works
20,447 m TBM tunnel works
13,888 pieces segment works
was completed.
Expected project completion: May 2025.
NUSFALAU - SUPLACU DE BARCAU 3B5 (KM 66 + 500 - KM 80 + 054.044)
MOTORWAY DESIGN AND CONSTRUCTION PROJECT
The project consists of the construction of a 13.5 km 2x2 motorway with 5 bridges
and 7 overpass structures. The main work items include Design, Earthworks, Art
Structures, Infrastructure Transfers, Sub-base, Foundation and Hot Bituminous
Mixture and Bridge and Overpass Structures. The project signing date is 30
September 2020 and the design works start date is February 2021.
In 2022, for the Project: In the Project as of the end of 2022, total:
148,351 m stripping excavation works 235,039 m stripping excavation works
3
3
3
206,206 m stabilization works 272,383 m stabilization works
3
3
173,360 m cut excavation works 215,849 m cut excavation works
3
3
1,159 m filling works 1.187.851 m filling works
3
6,458 m pile works 11,278 m pile works
33,647 m reinforced concrete works 34,565 m reinforced concrete works
3
3
680 m culvert works 805 m culvert works
299,468 m ballast works 299,468 m ballast works
3
3
3
3
54,221 m stabilised ballast works 54,221 m stabilised ballast works
44,498 tons bituminous base works 44,498 tons bituminous base works
19,783 tons binder works 19,783 tons binder works
169 tons wear works was completed. 169 tons wear works was completed.
Algeria Souk Tleta Dam Project
Expected project completion: September 2023.