PROJECTS: ON-GOING AND OUT OF PTO TIZI OUZOU BOUIRA INTERSECTION MOTORWAY - PTO PROJECT
The 48 km long connection highway between Tizi Ouzou-Bouira in Algeria is
THE SCOPE OF REPORT operated by Özgün-Nurol Partnership, and within the scope of the Project, 48 km
of highway, a total of 2 x 1.670 meters of double tube tunnel, 21 viaducts, and other
structures, infrastructure and drainage system manufacturing will be completed.
KONYA EĞİSTE HADİMİ VIADUCT PROJECT The section of the Project between km: 0+000-20+000 and 4+500–10+000 have
The tender related to the Eğiste Hadimi Viaduct has been carried out by the been opened to traffic, and the remaining parts are being constructed.
General Directorate of Highways. The contract has been awarded to Nurol
Construction at the end of 2016. Within the scope of the Project, a viaduct with a
total length of 1,372 meters and a width of 25 meters will be constructed; and it In 2022, for the Project:
1,898,466 m cut excavation works
3
will be one of the world’s largest balanced cantilever viaducts. The superstructure 1,084,403 m filling works
3
will be constructed on 2 abutments and 8 piers with varying heights between 31 to 78,085 m reinforced concrete works
3
3
155 meters. The project was completed in November 2022. 40,650 m tunnel pavement concrete works
10,481 tonnes of superstructure cold mix works
In 2022, for the Project: In the Project as of the end of 2022, total: 4,180 tonnes of superstructure hot mix works
3
407 m filling works 514,144 m cut excavation works was completed.
3
3
9,966 m reinforced concrete works 35,800 m filling works
3
8,013 tons of reinforcement works 11,945 m bored pile works In the Project as of the end of 2022, total:
3
1,181 tons post-tensioning works 138,476 m reinforced concrete works 18,348,736 m cut excavation works
3
3
5,769 m guardrail 37,152 tons of reinforcement works 4,173,098 m filling works
3
253,653 kg pedestrian railing 3,028 tons post-tensioning works completed. 476,120 m reinforced concrete works
3
5,488 m wire fence 5,769 m guardrail 630,742 m tunnel excavation works
3
27,440 m asphalt (wearing) layer completed. 253,653 kg pedestrian railing 72,273 m tunnel pavement concrete works
2
5,488 m wire fence 243,401 tons of superstructure cold mix works
27,440 m asphalt (wearing) layer completed 302,702 tons of superstructure hot mix works Pto Tizi Ouzou Bouira Intersection
2
was completed. Motorway - Pto Project
Expected project completion: December 2026.
B1070 TEST BUILDING CONSTRUCTION PROJECT
B1070 Test Building contract signed with TUSAS in September 2022 included the
turnkey construction of a steel construction test building with a closed area of 14.258m
2
and a height of 60 metres, and a reinforced concrete administrative building.
In 2022, for the Project:
54,061 m cut excavation works
3
77,737 m filling works
3
26,055 m reinforced concrete works
3
20,867 m bored pile works
4,545 tonnes of steel construction works
2
50,167 m plating works
In the Project as of the end of 2022, total:
54,061 m cut excavation works
3
3
77,737 m filling works
26,055 m reinforced concrete works
3
20,867 m bored pile works
4,545 tonnes of steel construction works
B1070 Test Building Project 50,167 m plating works
2
Eğiste Hadimi Viaduct Project
Expected project completion: March 2024.