Saadiyat Island Project, Museum District
Infrastructure – Service Tunnel
• Location: Abu Dhabi / UAE • Type of Work: Cut and Cover Service
Tunnel • The project, located in Abu Dhabi/UAE, is comprised of
design and build works for 1,5 km long service tunnel. The service
tunnel has security check points at both Entry/Exits of the tunnel.
The service tunnel serves the Saadiyat Cultural District developments
and provides underground access to all of these new developments
through their Security Screening Facility (SSF).
Boukhroufa Dam Project
• Location: El Tarf / ALGERIA • Type of Work: Earth fill dam with
central clay core • Reservoir Volume: 125,000,000 m • Height from
3
Foundation: 87 m • Boukhroufa Dam is under construction by Nurol
Construction Co. within the El Tarf province of Algeria. It is located
on the Boukhroufa Stream, 9 km south of the city of Bouteldja, with
3
a view to provide 125 hm of irrigation water to the agricultural lands
in the region. The dam is a clay core earth fill dam and it will rise 87
m high from the foundation. Once completed, its reservoir will have a
3
125,000,000 m storage capacity. Within the project scope, 2.200.000
3
3
m excavation, 4.800.000 m fill, 82.000 m concrete and 2.800 tons
3
of steel will be carried out.
Hasankeyf Group Bridges Projects
• Location: Hasankeyf- Batman/ TURKEY • Type of Work: 3 motorway
bridges • The project was designed to relocate the existing roads in the
region that will be immersed once the construction of Ilısu Dam and
Hydroelectric Power Plant are completed. The project scope includes
the constructions of three bridges, namely Hasankeyf-1, Hasankeyf-2
and Başur. Hasankeyf-1 and Hasankey-2 are to provide a passage over
the River Tigris, while the Başur Bridge is aimed to replace the “Old”
Başur Bridge due to relocation of existing roads to the old bridge.
Construction of West Mangrove Channel and Sand
Beach, and Extension of the Inner Canal Seawall
• Location: Abu Dhabi / UAE • Type of Work: Mangrove Channel &
Sand Beach • Project scope covers the clearance of the field including
the removal of handrail capping and now defunct temporary facilities;
excavation of the West Channel; creation of the sand beaches;
construction of seawalls of inner canals, the connection to the City of
Lights district and mangrove regeneration works.
46 | Infrastructure Projects