PROJE ADI | : | Kürtün Dam and Hydroelectric Power Plant |
LOCATION | : | Harşit River – Gümüşhane / TURKEY |
TYPE OF WORK | : | Concrete face rockfill dam |
DAM BODY VOLUME | : | 3.200.000 m³ |
RESERVOIR VOLUME | : | 108,2 billion m3 |
INSTALLED POWER | ||
CAPACITY | : | 85 MW |
POWER PLANT TYPE | : | Underground type power plant (2 ea. Francis type turbine) |
ANNUAL POWER | ||
PRODUCTION | : | 198 GWh |
HEIGHT FROM | ||
FOUNDATION | : | 133 m |
CREST LENGTH | : | 380 m |
DESCRIPTION |
||
The dam has two spillway tunnels of 314 m and 357 m lengths (diameter: 12 m) two diversion tunnels of 702 m and 742 m lengths (diameter: 5 m) and one bottom outlet tunnel of 646 m length (diameter: 5 m). In addition, 9 hydraulic tunnels of 3.852 m total length with excavation diameters varying 4,40 m and 8,40 m were also completed |